Energy transition model in Thermal Power Plants. Waste gas recovery
Aboño Thermal PP. Coal to gas conversion.

Spain

The Aboño Thermal Power Plant, owned by EDP Spain, is a conventional cycle thermoelectric facility located next to the port of Gijón, in the municipality of Carreño, in Asturias. It consists of two thermal groups, in total 921 MW, which currently use coal as the main fuel. These facilities must adapt environmentally to the National Transitional Plan, in accordance with the European Directive on Emissions. The Aboño power plant is located near the Arcelor-Mittal steelworks in Gijón, which is generating a surplus of blast furnace gas of around 50% (an amount that will increase as a result of the ongoing improvements to the facilities). The gas is being burned in flares and an alternative solution is required. An agreement between EDP and Arcelor-Mittal will resolve both issues.

In accordance with the foregoing, EDP plans to undertake a project for the reconversion of Group 1 of the Aboño power plant, moving from coal as the main fuel to the steel gases (blast furnace gas and coke battery gas) surpluses of the Arcelor-Mittal factory, which have already been used in the plant since 1975 as supplementary fuel. Additionally, Group 1 will use natural gas as a support fuel, both for the start-up and stabilization of the group, and when the availability of steel gases is not enough to maintain its minimum load. This modification is associated with environmental improvements such as reducing polluting emissions into the atmosphere (SO2, NOx and particles), reducing GHG emissions (CO2), reducing waste generation (mainly ash and slag), reducing the demand for water and, consequently, the waste generated.

The solution proposed for the projected conversion consists of:

  • Dismantling of facilities associated with coal and liquid fuels.
  • Modification of the gaseous fuel supply systems (steel gases and natural gas) in the Thermal Power Plant.
  • Replacing existing coal burners in the boiler with others to burn gaseous fuels.
  • Carrying out various actions in the air-smoke circuits to adapt them to the new fuels and comply with the environmental requirements for emissions into the atmosphere that may be imposed on the project.
  • Extension of the life of the boiler, to keep it operational for another 25 years.
  • Modernization of the turbo-group and auxiliary equipment according to the new combustion conditions in the boiler, in order to optimize its performance and the gross power delivered.
  • Carrying out renovation, maintenance and work to extend life on other equipment and BOP systems of the group, so that it can function in safe and reliable conditions.

IDOM has been contracted by EDP to provide support during the execution of the project. The contracted services initially include the preparation of the Basic Engineering and the Specification for Contracting (under an EPC agreement) of the works related to the modifications of the boiler. Associated with this, EDP has also contracted IDOM to undertake a series of complementary works such as the preparation of a 3D model of the existing boiler, the dismantling plan of the facilities linked to the use of coal, a study of the capacity and operation of the gasometer, the structural check of the structure of the boiler and the air-smoke circuit, and the functional modeling of the water-steam circuit.

Coal-fired Power Plants

  • Share on Facebook
  • Share with Twitter
  • Share with Linkedin

SCOPE:
Basic Engineering
Technical Specification for EPC Contracting

  • Abono1_Power_Plant_Coal_to_Gas_Conversion_Spain_EDP_IDOM_00