Revamping works in the WTE Plant of Sant Adria del Besos, Barcelona

Spain

TERSA has hired Ros Roca for the substitution of the 3 grates and slag extractor due to a change in the wastes to be treated. Technology was done by Hitachi Zosen Inova (HZI).

The Project comprises the following equipment:

  • Feed Hopper
  • Hydraulic station
  • 3 new grates and corresponding cooling system
  • Slag extractor
  • Ventilation system
  • Electrical Works
  • Control works

The functions performed by IDOM were:

  • Layout definition, closely working with Hitachi
  • Equipment integration into existing geometry
  • Integration of all project disciplines according to Hitachi’s specifications
  • Structural design and reinforcement of the existing structure
  • Grate supporting new steel structure and furnace steel structure reinforcement
  • Electrical detail engineering
  • Control system detail engineering
  • Purchasing management
  • Building permit
  • Construction management
  • Assistance to commissioning

Waste to Energy

  • Share on Facebook
  • Share with Twitter
  • Share with Linkedin

CLIENT:
TERSA

SCOPE:
Assistance - Permit Phase
Basic Engineering
Commissioning
Detailed Engineering
Procurement Management
Works supervision