0 %

Sorry, there are currently no results available

Projects

News

Recent Publications

Vídeos

Offices

Revamping works in the WTE Plant of Sant Adria del Besos, Barcelona

Spain

TERSA has hired Ros Roca for the substitution of the 3 grates and slag extractor due to a change in the wastes to be treated. Technology was done by Hitachi Zosen Inova (HZI).

The Project comprises the following equipment:

  • Feed Hopper
  • Hydraulic station
  • 3 new grates and corresponding cooling system
  • Slag extractor
  • Ventilation system
  • Electrical Works
  • Control works

The functions performed by IDOM were:

  • Layout definition, closely working with Hitachi
  • Equipment integration into existing geometry
  • Integration of all project disciplines according to Hitachi’s specifications
  • Structural design and reinforcement of the existing structure
  • Grate supporting new steel structure and furnace steel structure reinforcement
  • Electrical detail engineering
  • Control system detail engineering
  • Purchasing management
  • Building permit
  • Construction management
  • Assistance to commissioning

Waste to Energy

  • Share on Facebook
  • Share with Twitter
  • Share with Linkedin

CLIENT:
TERSA

SCOPE:
Assistance - Permit Phase
Basic Engineering
Commissioning
Construction Management
Detailed Engineering
Procurement Management

  • TERSA_WTE_Idom